This paper descries the effort to bring the Tampa Bay desalination plant online applying for more than 22 permits for construction and subsequent operations. In addition to this regulatory oversight, a cumulative impact analysis, several predictive modeling projects, and 6 independent assessments of pilot plant operations were undertaken to provide assurance that adverse environmental impacts were not anticipated.